Time and Work – Quantitative Aptitude – IBPS SBI Bank PO/ Clerk, SSC CGL, CAT, MBA, LIC AAO

1

Part 1 : Basic Questions


Leave A Reply

Your email address will not be published.

1 Comment

  1. Gourab chakraborty says

    Sir how can solve this type of question?
    Q- A can complete a piece of work in 9 days and B in 12 days respectively.If they work for a day alternately,in how many days the work would be finished,if A begins the work ?

    Sir please solve in your tricks as u mentioned in old classes…

IBPS Clerk 2017 Video Lecturesx